Market Role
Austin-San Antonio is a Central Texas data-center and powered-land corridor, not a strict CBSA market. Use this page when a source defines the market across the Austin and San Antonio orbit, especially where demand follows utility territory, land availability, and power-delivery path rather than conventional metro boundaries.
Source: CBRE Austin-San Antonio Data Center Market H1 2025 adds the first normalized market benchmark for this combined lane. CBRE reported 2.3% vacancy, 97% preleased under-construction capacity, and 462.0 MW under construction in H1 2025 (market_observations.id=44034-44036). Treat that as evidence of a tight and rapidly expanding data-center market, not as blanket proof that every Austin or San Antonio exurban land site deserves a powered-land premium.
Market Metrics
| Metric | Value | Evidence |
|---|---|---|
| Vacancy | 2.3% | CBRE H1 2025 source note / market_observations.id=44034 |
| Under-construction preleased share | 97.0% | CBRE H1 2025 source note / market_observations.id=44035 |
| Under-construction capacity | 462.0 MW | CBRE H1 2025 source note / market_observations.id=44036 |
Geography Read
CBRE's market-trend text points to two useful geography screens. First, developers were focused on the northeast suburbs of Austin where available land is served by Oncor. Second, increased Austin-area interest was pushing activity south of Austin into Lower Colorado River Authority territory. That supports a Central Texas service-territory lens rather than a pure downtown Austin, downtown San Antonio, or I-35 midpoint lens.
Existing repo coverage already has adjacent watchlist items: Powerhouse / Caldwell County near Uhland and Microsoft's reported Castroville / Medina County project west of San Antonio. Those examples should be read through this market benchmark, but they still require site-specific utility, water, entitlement, tenant, and capital-stack proof before they become underwritable inventory.
Colovore Hutto Data Center is a more specific Hutto project-stage marker: Texas TDLR lists a 192,694-SF privately funded building, a $280 million estimated cost, and projected December 2026–December 2028 construction dates. Its filing status is Project Registered, with no tenant assigned. Colovore separately markets 40 MW and a 2026–2027 pre-leasing window. Keep the filed project dimensions and sponsor-marketed capacity separate from this market's CBRE/Avison Young metrics; neither verifies energized local capacity, tenant demand, or operating inventory. See Source: Connect CRE Colovore Hutto Data Center 2026.
Avison Young's reviewed Q1 2026 U.S. data-center overview adds a source-defined Austin market
observation: 1,909 MW of positive colocation net absorption in Q1 2026. This is a named-market
absorption row within Avison Young's tracked universe, not available power, delivered inventory,
or a Planning Area total. The U.S. rows remain separate and are not blended into this Central Texas
benchmark.
Boundary Conditions
This page is a data-center market benchmark and powered-land router. It should not be used to overwrite Austin's office / multifamily normalization story or San Antonio's workforce-housing / affordability thesis. The relevant investment question is whether a specific site can secure power, water / cooling, fiber, zoning, community acceptance, and tenant demand faster than competing Central Texas alternatives.
Portfolio Fit
The best-fit capital is specialized digital-infrastructure, utility-aware land, and industrial infrastructure capital. Conventional multifamily, office, retail, and warehouse investors should use this page as context only when the subject site has real exposure to power-delivery, data-center labor, infrastructure construction, or tax-base effects.
Related Pages
- Austin
- San Antonio
- Texas AI and Industrial Infrastructure Opportunity Map
- Powered Land and Grid Advantage
- Digital Infrastructure Real Estate
- National Digital Infrastructure Capital Deployment 2026
- Data Center Underwriting and Powered Land
- East Austin Tesla and Airport Corridor
- Williamson County Semiconductor Corridor
Review Notes
- 2026-06-30 review: promoted as reviewed Austin-San Antonio data-center / powered-land coverage anchored to CBRE's public H1 2025 profile, preserved public-reader text, BeautifulSoup direct-capture diagnostics, and structured observations. Use as a source-scoped Central Texas digital-infrastructure benchmark; utility capacity, tariff treatment, water, entitlement status, site control, tenant-credit, transactions, lease economics, and parcel-level claims still require local source notes, structured observations, utility records, entitlement records, lease records, or primary records before public/API or pro forma use.
- 2026-08-28 review: added the qualified Avison Young Q1 2026 Austin absorption row. The claim is source-defined and independently claim-reviewed; it does not establish powered-land capacity, civic-neighborhood performance, or a synthetic Austin-San Antonio series.
Sources
- Source: CBRE Austin-San Antonio Data Center Market H1 2025
- Source: Powerhouse Data Centers Caldwell County Data Center Proposal
- Source: Reports: Microsoft Plans $400M Data Center in Castroville, Texas
- Source: Avison Young Q1 2026 U.S. Data Center Market Overview
- Source: Connect CRE Colovore Hutto Data Center 2026
Location-quality diligence routes
The geography-level Austin Houston Public Safety Evidence Comparison 2025 and Austin Houston School Boundary Evidence Comparison 2026 pages provide source-custodied location-quality routes for this market. They are separate from the operating-market evidence on this page: citywide or council-district safety observations do not establish property or submarket safety rates, and school-boundary resources do not establish school quality, assignment, rent premium, or demand. Carry current subject-address safety, school-year, access, insurance, and public-realm diligence alongside any operating-market underwriting.
Household-context evidence route
The source map Austin Houston Household Context Evidence 2026 links Austin’s planning-area ACS proxy and Houston’s Super Neighborhood housing-structure extraction. These source-defined civic observations are context only; they do not establish property rents, occupancy, NOI, absorption, valuation, tenant demand, or a provider-defined operating market. Where this page’s geography does not match a source-defined label, obtain current municipality, tract, parcel, and property evidence instead of borrowing a nearby civic total.
Castroville application — filing status and service evidence
Source: Reports: Microsoft Plans $400M Data Center in Castroville, Texas is a January-reported Medina County project lead, with a later-read accessibility registry that has different estimates. Neither a scheduled date nor Review Complete proves construction progress, local entitlement, energized capacity or a tenant lease. Use San Antonio, Data Center Underwriting and Powered Land, Energy Infrastructure and CRE and CRE Capital Markets to reconcile project history, parcel rights, utility obligations, phase acceptance and funding. Keep this project separate from CBRE’s combined corridor and Avison Young’s named Austin market measurements.