Chicago is a real CBRE-tracked primary data-center market, but the market is best read through power delivery rather than ordinary metro location logic. CBRE's H1 2025 profile already showed AI demand and project-pressure signals: Prime Data Centers leased 72 MW to an AI-related tenant, and two Yorkville projects were seeking approval for 38 buildings and 3+ GW of power. CBRE's H2 2025 profile then says Chicago vacancy fell to 1.9%, projects delivering by year-end 2027 have less than 10% vacancy, and no contiguous 5 MW-plus space is available. CBRE's Q1 2026 global data-center report later kept Chicago among the tight major markets, with 2.2% vacancy in its Q1 2026 table.

The constraint is ComEd and transmission execution. CBRE says ComEd-served projects face power delivery delays until 2032 or later, and that ComEd now requires 10-year letters of credit to back transmission revenue on projects of 50 MW or more. That turns Chicago data-center underwriting into a utility-credit and speed-to-power exercise, not just a tenant-demand or rent-growth screen.

Transaction and policy update (September 2026)

The Real Deal reports a $750M September acquisition by GI Partners of the 189,000-SF data-center facility at 800 East Devon Avenue in Elk Grove Village. The same article says HMC Capital's subsidiary paid $440M for the former warehouse in 2024 and had another $272M contingent on conversion. Treat the reported trade as a single asset event: the deed, property identifier, price allocation, conversion spend, and lease economics are not in the retained evidence. See 800 East Devon Avenue Data Center.

The regulatory picture is jurisdiction-specific. Illinois DCEO stopped processing new data-center incentive applications on July 1, while honoring earlier agreements; this does not stop construction. Chicago's proposed one-year city-wide permit moratorium was introduced and referred to committee on September 23, but the City Clerk's record shows no final action. Lake County adopted an eight-month moratorium only for unincorporated county areas, through May 2027, and reported no pending proposals there at adoption. Do not apply these separate measures to Elk Grove Village or all of Chicagoland. See Source: Illinois Data Center Policy and 800 East Devon Sale 2026.

Underwriting Read

GateCurrent readUnderwriting use
H1 AI leasingCBRE H1 2025 reports a 72 MW Prime Data Centers lease to an AI-related tenant.Treat AI demand as source-supported, but still require tenant credit, lease structure, power delivery, and energization timing before underwriting value.
H1 Yorkville approvalsCBRE H1 2025 says two Yorkville projects were seeking approval for 38 buildings and 3+ GW of power.Use as approval-stage pipeline pressure, not delivered inventory or approved capacity.
Vacancy / contiguous spaceCBRE H2 2025 reports 1.9% vacancy and no contiguous 5 MW-plus space.Treat existing supply as scarce, but verify whether the requirement is retail colocation, wholesale, hyperscale, or owner-occupied.
Pipeline preleasingCBRE says projects delivering by year-end 2027 have less than 10% vacancy.Use as preleasing support, not as proof that every pipeline project is financeable.
Power deliveryComEd-served projects face delivery delays until 2032 or later.Require interconnection, transmission, substation, energization, and utility-cost proof before pricing powered-land premiums.
Credit supportComEd requires 10-year letters of credit for projects of 50 MW or more.Underwrite sponsor credit, balance-sheet capacity, and utility revenue-security obligations as part of site feasibility.
Exurban power sitesNew development is moving outside the suburbs toward 500 MW-plus power sites.Treat Minooka, Joliet, and other exurban sites as power-first campus nodes, not conventional suburban industrial locations.

Portfolio Fit

Chicago fits data-center capital that can solve utility process, credit support, and exurban power-site execution. It is not a generic metro-growth allocation. The useful investment lens is scarce existing space plus difficult future energization, with location becoming secondary to power availability once the project moves outside the core suburban data-center clusters.

Sources

  • Source: CBRE Chicago Data Center Market H2 2025
  • Source: CBRE Chicago Data Center Market H1 2025
  • Source: CBRE Global Data Center Trends 2026

Election, incentives and permit authority as of November 6

Illinois Election and CRE Policy Outlook 2026 separates political sentiment from operative restrictions. DCEO stopped processing new incentive applications July 1 under a June directive; this predates the election and does not ban construction. Chicago matter O2026-0028856 remains in committee in the retained capture. Its one-year pause is proposed, with permit/use distinctions, and the mayor letter's 2025 date conflicts with the matter's 2026 introduction. Bloomington and Joliet Township questions are advisory and have different footprints and authority.

Existing energized facilities, permitted expansions, valid incentive rights and speculative land require separate underwriting. Do not infer a universal scarcity premium, cross-border relocation or project cancellation. Require current ordinance, executed utility delivery, water/sewer, tenant credit and incentive MOU. See source-il-dceo-current-datacenter-program-revision-20261106, source-il-chicago-datacenter-ordinance-current-revision-20261106, source-il-chicago-datacenter-pause-proposed-ordinance-o2026-0028856 and source-il-joliet-township-enacted-advisory-referral-resolution2026-08.